DOC 00001 Published On: 04/01/2025
Question: Does DTE have a list of preferred vendors and/or equipment manufacturers for PPA agreements?
Answer: No. DTE does not have a preferred list of vendors and/or equipment manufacturers for PPA agreements. Please see the Pro Formas for a list of currently approved vendors.
DOC 00002 Published On: 08/28/2025
Question: Are respondents able to add/remove projects after submitting them to DTE through the Notice of Intent process?
Answer: Yes, this is acceptable.
DOC 00003 Published On: 08/28/2025
Question: Are Self-Build teams required to complete Exhibit C: Respondent's Financial Information or are they exempt from providing credit-related data?
Answer: To ensure all bidders are treated on an equal footing, self-build teams will be required to provide Exhibit C.
DOC 00004 Published On: 09/25/2025
Question: If the projects have changed from the original NOI submitted back in June, do we need to submit a new NOI (Exhibit B) and when?
Answer: No, you don't need to submit a new NOI. We look forward to receiving your proposal by the November 3 due date.
DOC 00005 Published On: 09/30/2025
Question: Good morning, For the upcoming DTE All-Source RFP, wondering what the timeline is for release of Exhibit M - PPA Wind and Solar, and Exhibit O - TA Energy Storage System. Thanks!
Answer: Per the posted instructions, these are currently available in the Pro Forma PPA section of the RFP website located at https://dtee-irp-2025allsourcerfp.com/Pro-Forma-Agreements - to access, an NDA must be executed per the instructions on this page. User access will be sent afterwards via e-mail.
DOC 00006 Published On: 10/20/2025
Question: Section 3.9 of the RFP states any exceptions to the "Non-Negotiable" section of the Agreement are not permitted and will result in disqualification. Can DTE please share what sections in Exhibit P - Purchase and Sale Agreement are considered non-negotiable?
Answer: DTE has not identified any provisions in Exhibit P – Purchase and Sale Agreement as non-negotiable at this time. However, certain terms may be designated as non-negotiable during the negotiation phase to address specific requirements or risks associated with the Project.